Stage 7 Progress

The initial clearing of the site is now complete.

We are currently finalising the selection of a contractor to carry out the civil works which will include the placement of a new water main for the village.

It is hoped certification from the Coffs Harbour City Council to commence the civil works will arrive next week, allowing the civil works to commence in the soon.

Traffic management will be in place during this period.

The main construction package will go to tender Friday 28th September with an expectation that a builder can establish the site December.

Frequently Asked Question – What have we done with the trees?

Rather than waste them, they have been chipped and stockpiled onto the old nursery site. There is approx. 170 cubic metres of mulch valued at well over $5000 that will be used in the gardens throughout the village.